Occupational Hygiene Monitoring Survey Report
Inventory Of Asbestos In Place And Asbestos Risk Assessment Report
Karoo Agri Processing · Beaufort West Pack House
27 Aug 2026
Project Number AS-2026-498 · Revision 0
Survey Information Details
| Report Number | AS-2026-498-R0 |
| Project Number | AS-2026-498 |
| Client | Karoo Agri Processing |
| Site / Premises | Beaufort West Pack House |
| Physical Address | Plot 22, N1 South, Beaufort West |
| Survey Date | 27 Aug 2026 |
| Stress Factor | Asbestos In Place |
| Surveyor | Pieter Botha |
| Technical Signatory | Riaan de Villiers |
| Applicable Legislation | Asbestos Abatement Regulations, 2020 |
| Occupational Exposure Limit | Risk Categorisation Per Annexure A Risk Categorisation Sheet |
1.0 Executive Summary
Karoo Agri Processing contracted The Safety Network (Africa) (Pty) Ltd to conduct a asbestos inventory survey at Beaufort West Pack House, Plot 22, N1 South, Beaufort West. The survey was conducted on 27 Aug 2026 by Pieter Botha.
Three asbestos containing materials were recorded. One item is in poor condition and is prioritised for removal.
2.0 Purpose Of The Survey
- Identify and record all asbestos containing materials in place
- Assess the condition and risk of each identified material
- Compile an asbestos register and risk assessment for the premises
- Recommend a prioritised asbestos management plan
3.0 Contents Of Report
- 1.0Survey Information Details
- 2.0Abbreviations And Definitions
- 3.0Executive Summary
- 4.0Introduction
- 5.0Purpose Of The Survey
- 6.0Survey Methodology
- 7.0Inventory Of Asbestos In Place And Asbestos Risk Assessment
- 8.0Discussion Of Results And Outcome Of Asbestos Risk Assessment
- 9.0Recommendations
- 10.0Conclusion
- 11.0Annexures To The Report
4.0 Instruments Used
| Instrument | Serial Number | Calibration Due |
|---|---|---|
| Gilian 5000 pump | GIL-4402 | 04 Nov 2026 |
| Gilian 5000 pump | GIL-4407 | 22 Oct 2026 |
| SKC Airchek TOUCH | SKC-2210 | 27 Sept 2026 |
5.0 Results And Discussion
| Item | Location | Material | Asbestos Type | Condition | Risk Category | Priority |
|---|---|---|---|---|---|---|
| A-01 | Main Building Roof | Cement Roof Sheeting | Chrysotile | Fair | Medium | Manage In Place |
| A-02 | Pool House Roof | Cement Slate Tiles | Chrysotile | Poor | High | Remove |
| A-03 | Plant Room | Pipe Lagging | Amosite | Good | Low | Monitor |
Three asbestos containing materials were recorded. One item is in poor condition and is prioritised for removal.
6.0 Recommendations
- Remove the pool house slate tiles using a registered asbestos contractor
- Maintain the asbestos register and review it every 24 months
- Label and manage remaining materials in place
- Brief maintenance staff before any work near recorded materials
7.0 Conclusion
Asbestos is present in place and must be managed under a documented asbestos management plan.
8.0 Annexures To The Report
- Annexure A — Risk Categorisation Sheet
- Annexure B — Certificate Of Approval As A Department Of Employment And Labour Approved Inspection Authority
- Annexure C — Laboratory Results For Samples Analysed By Electron Microscopy
- Annexure D — Photo Log And Description Of Asbestos Cement Materials
- Annexure E — Site Plan
- Annexure F — Floor Plans And Indication Of Asbestos In Place
- Annexure G — SAIOH Certificates
The Safety Network (Africa) (Pty) Ltd
T/A SafeNet Africa
Dept. of Employment and Labour: AIA OH 0242 CI062
Signature of Technical Signatory
Riaan de Villiers
Signature of Surveyor
Pieter Botha