KF

Report Preview

SURVSNA AS 05 ASBESTOS MONITORING
Report NumberAS-2026-511-R0
Page NumberPage 1 of 25
RevisionsRevision 2
Survey Date11 Sept 2026
SafeNet Africa

Occupational Hygiene Monitoring Survey Report

Asbestos Air Monitoring Survey Report

Cape Coastal Property Group · Sea Point Block B

11 Sept 2026

Project Number AS-2026-511 · Revision 2

Survey Information Details

Report NumberAS-2026-511-R0
Project NumberAS-2026-511
ClientCape Coastal Property Group
Site / PremisesSea Point Block B
Physical Address112 Beach Rd, Sea Point, Cape Town
Survey Date11 Sept 2026
Stress FactorAsbestos
SurveyorPieter Botha
Technical SignatoryRiaan de Villiers
Applicable LegislationAsbestos Abatement Regulations, 2020 · SANAS Accredited Inspection Body
Occupational Exposure LimitOEL-TWA 0.2 Regulated Asbestos Fibres Per Millilitre Of Air

1.0 Executive Summary

Cape Coastal Property Group contracted The Safety Network (Africa) (Pty) Ltd to conduct a asbestos monitoring survey at Sea Point Block B, 112 Beach Rd, Sea Point, Cape Town. The survey was conducted on 11 Sept 2026 by Pieter Botha.

All airborne asbestos fibre concentrations measured were below the prescribed OEL during removal activities.

2.0 Purpose Of The Survey

  1. Conduct air monitoring during asbestos work activities
  2. Compare measured airborne fibre concentrations with the prescribed OEL
  3. Inspect the site against the approved asbestos plan of work
  4. Recommend action steps to reduce exposure to below the OEL

3.0 Contents Of Report

  1. 1.0Executive Summary
  2. 2.0Table Of Contents
  3. 3.0List Of Tables, Figures And Diagrams
  4. 4.0List Of Terms And Abbreviations
  5. 5.0Introduction
  6. 6.0Monitoring Methods And Procedure Followed
  7. 7.0Results And Discussion
  8. 8.0Recommendations
  9. 9.0Conclusion
  10. 10.0Indemnity And Signatures
  11. 11.0References
  12. 12.0Annexures To The Report

4.0 Instruments Used

InstrumentSerial NumberCalibration Due
Gilian 5000 pumpGIL-440204 Nov 2026
Gilian 5000 pumpGIL-440722 Oct 2026
SKC Airchek TOUCHSKC-221027 Sept 2026

5.0 Results And Discussion

Sample No.PositionTypeVolume LFibres/mlOELOEL Exceeded
AS-01Enclosure ExteriorStatic480<0.010.2No
AS-02Removal OperativePersonal2400.040.2No
AS-03Waste Loading AreaStatic4800.020.2No
AS-04Clearance BackgroundStatic480<0.010.01No

All airborne asbestos fibre concentrations measured were below the prescribed OEL during removal activities.

6.0 Recommendations

  1. Maintain enclosure integrity and negative pressure during removal
  2. Continue decontamination discipline at the hygiene unit
  3. Remove the waste skip from site on completion of works
  4. Issue the clearance certificate once all waste has been removed

7.0 Conclusion

Asbestos work was performed with airborne fibre concentrations controlled below the OEL.

8.0 Annexures To The Report

  • Annexure A — Certificate Of Approval As A Department Of Employment And Labour Approved Inspection Authority
  • Annexure B — SANAS Schedule Of Accreditation
  • Annexure C — Laboratory Analysis Certificates
  • Annexure D — Calibration Certificates
  • Annexure E — Photo Log
  • Annexure F — Approved Asbestos Plan Of Work

The Safety Network (Africa) (Pty) Ltd

T/A SafeNet Africa

Dept. of Employment and Labour: AIA OH 0242 CI062

Signature of Technical Signatory

Riaan de Villiers

Signature of Surveyor

Pieter Botha