Occupational Hygiene Monitoring Survey Report
Asbestos Air Monitoring Survey Report
Cape Coastal Property Group · Sea Point Block B
11 Sept 2026
Project Number AS-2026-511 · Revision 2
Survey Information Details
| Report Number | AS-2026-511-R0 |
| Project Number | AS-2026-511 |
| Client | Cape Coastal Property Group |
| Site / Premises | Sea Point Block B |
| Physical Address | 112 Beach Rd, Sea Point, Cape Town |
| Survey Date | 11 Sept 2026 |
| Stress Factor | Asbestos |
| Surveyor | Pieter Botha |
| Technical Signatory | Riaan de Villiers |
| Applicable Legislation | Asbestos Abatement Regulations, 2020 · SANAS Accredited Inspection Body |
| Occupational Exposure Limit | OEL-TWA 0.2 Regulated Asbestos Fibres Per Millilitre Of Air |
1.0 Executive Summary
Cape Coastal Property Group contracted The Safety Network (Africa) (Pty) Ltd to conduct a asbestos monitoring survey at Sea Point Block B, 112 Beach Rd, Sea Point, Cape Town. The survey was conducted on 11 Sept 2026 by Pieter Botha.
All airborne asbestos fibre concentrations measured were below the prescribed OEL during removal activities.
2.0 Purpose Of The Survey
- Conduct air monitoring during asbestos work activities
- Compare measured airborne fibre concentrations with the prescribed OEL
- Inspect the site against the approved asbestos plan of work
- Recommend action steps to reduce exposure to below the OEL
3.0 Contents Of Report
- 1.0Executive Summary
- 2.0Table Of Contents
- 3.0List Of Tables, Figures And Diagrams
- 4.0List Of Terms And Abbreviations
- 5.0Introduction
- 6.0Monitoring Methods And Procedure Followed
- 7.0Results And Discussion
- 8.0Recommendations
- 9.0Conclusion
- 10.0Indemnity And Signatures
- 11.0References
- 12.0Annexures To The Report
4.0 Instruments Used
| Instrument | Serial Number | Calibration Due |
|---|---|---|
| Gilian 5000 pump | GIL-4402 | 04 Nov 2026 |
| Gilian 5000 pump | GIL-4407 | 22 Oct 2026 |
| SKC Airchek TOUCH | SKC-2210 | 27 Sept 2026 |
5.0 Results And Discussion
| Sample No. | Position | Type | Volume L | Fibres/ml | OEL | OEL Exceeded |
|---|---|---|---|---|---|---|
| AS-01 | Enclosure Exterior | Static | 480 | <0.01 | 0.2 | No |
| AS-02 | Removal Operative | Personal | 240 | 0.04 | 0.2 | No |
| AS-03 | Waste Loading Area | Static | 480 | 0.02 | 0.2 | No |
| AS-04 | Clearance Background | Static | 480 | <0.01 | 0.01 | No |
All airborne asbestos fibre concentrations measured were below the prescribed OEL during removal activities.
6.0 Recommendations
- Maintain enclosure integrity and negative pressure during removal
- Continue decontamination discipline at the hygiene unit
- Remove the waste skip from site on completion of works
- Issue the clearance certificate once all waste has been removed
7.0 Conclusion
Asbestos work was performed with airborne fibre concentrations controlled below the OEL.
8.0 Annexures To The Report
- Annexure A — Certificate Of Approval As A Department Of Employment And Labour Approved Inspection Authority
- Annexure B — SANAS Schedule Of Accreditation
- Annexure C — Laboratory Analysis Certificates
- Annexure D — Calibration Certificates
- Annexure E — Photo Log
- Annexure F — Approved Asbestos Plan Of Work
The Safety Network (Africa) (Pty) Ltd
T/A SafeNet Africa
Dept. of Employment and Labour: AIA OH 0242 CI062
Signature of Technical Signatory
Riaan de Villiers
Signature of Surveyor
Pieter Botha